EDAC Release Calendar
Steps EDAC Timeline
Sandbox January 26 - Fall 2011
Market Trials May 2011 - August 2011
Preliminary EDAC Release Plan June 29, 2011
Participant Feedback July 13, 2011
Final EDAC Release Plan August 31, 2011 (Last Updated: Oct. 6, 2011)
Pre-Production Build October 6, 2011
Production Build (EDAC In Service Date) October 12, 2011
Production Build (New CRS) October 18, 2011
 