The Market Rule Amendments listed below have come into force and been published in the
current or previous baselines.
MR-00374 - Replacing the Temporary Suspension of CMSC for Constrained-Off Dispatchable Loads
Effective Date: |
Chapter 9 Sections 3.5.1C (delete), 3.5.1D (new), 3.5.2 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by October 28, 2010, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00372 - Settlements - CMSC and GCG Treatment for Aggregated Facilities
Effective Date: |
Chapters 7 & 9 |
Amendment Submission Q00 |
Amendment Proposal R00-R01
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by October 12, 2010, using the written submission form. |
Written Submission
Hydro One
|
Technical Panel Recommended Proposal R00-R01 |
The IESO Board decided against the adoption of this market rule amendment proposal at its meeting on November 11, 2010. However, the amendment proposal raised important policy questions regarding the GCG treatment for aggregated facilities that will require further discussion within the electricity sector.
|
MR-00371 - Settlements: Generation Station Service Rebate (GSSR)
Effective Date: |
Chapter 9 Sections 2.1A, 4.7G (new), 4.8 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 29, 2010, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00370 - Limiting CMSC Payments for Exporters and Dispatchable Loads
Effective Date: |
Chapter 9, sections 3.5.2, 3.5.6A(new) |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 29, 2010, using the written submission form. |
Written Submissions
OPG
Richard Penn
RBC
DC Energy
|
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00369 - Dispute Resolution - Changes to Dispute Resolution Panel
Effective Date: May 8, 2010 |
Chapter 3, sections 2.7.1, 2.7.1B, 2.7.40 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by March 25, 2010, using the written submission form. |
IESO Board Decision |
MR-00368 - Market Administration - Harmonized Sales Tax
Effective Date: |
Chapter 2, sections 1.2 and 3.1 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by March 4, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00367 - Settlements: Maximum Adjustment Period
Effective Date: |
Chapter 1,3,6,7,9,11 |
Amendment Submission Q00 |
On August 17, 2010 the Technical Panel determined that market rule amendment MR-00367 no longer warrants consideration. This amendment is now closed. |
MR-00366 - Compliance: Technical Feasibility Exceptions
Effective Date: May 8, 2010 |
Chapter 5, section 3.2A (new), Chapter 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R01
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by March 4, using the written submission form. |
Written Submissions
• TransAlta
• Hydro One |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IESO Board Decision |
MR-00365 - Settlement of Transmission Tariff for Embedded Generation Facilities
Effective Date: Jun 2, 2010 |
Chapter 6 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by January 14, 2010 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00364 - Allowing Non-Generation Resources to Provide Regulation
Effective Date: Jun 2, 2010 |
Chapters 5, 7 and 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R04 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by December 23, 2009, using the written submission form. |
Written Submissions
• John MacKenzie |
Technical Panel Recommendation on Amendment Proposal R00-R04 |
IESO Board Decision |
MR-00360 - CMSC resulting from IESO Action and Binding Net Interchange Scheduling Limit
Effective Date: Dec 9, 2009 |
Chapter 9, section 3 |
Amendment Submission Q00 |
Amendment Proposal R00 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by October 7, 2009, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00359 - Generation Facility Requirements - Change to Facilitate Connections
Effective Date: Mar 6, 2010 |
Appendix 4.2 |
Amendment Submission Q00 |
Amendment Proposal R00-R01 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Panel by December 23, 2009, using the written submission form. |
Written Submissions
• OPG
• General Electric
• Hydro One
|
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IESO Board Decision |
MR-00357 - Minor Amendment Omnibus 2009
Effective Date: Sep 9, 2009 |
Various chapters and section |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the MR-00357-R00 proposal and submit any comments to the Panel by April 30th, 2009 using the written submission form.
Stakeholders should be aware that because the proposed amendments are minor, if no substantive comments are submitted, a Panel recommendation of the proposal will automatically be made and the proposal submitted to the IESO Board for approval.
|
IESO Board Decision |
MR-00356 - Interim Changes to Real-Time and Day-Ahead Generation Cost Guarantee Programs
Effective Date: Dec 9, 2009 |
Chapters 7 and 9 |
Amendment Submission Q00 |
Amendment Proposal R00-R02 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 13, 2009, using the written submission form. |
Written Submissions
• Greenfield Energy Centre
• Greater Toronto Airports Authority
• Sithe Global |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision |
MR-00355 - Provision of Prudential Support: Sale of Registered Facilities and Expiring Letters of Credit
Effective Date: Mar 7, 2009 |
Chapters 2, 7, 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R03
The Technical Panel requests that stakeholders review the amendment submission and the draft amendment proposal and to provide comments by January 22, 2009 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
Written Submissions
Hydro One |
IESO Board Decision |
MR-00353 - IESO Publication Requirements - Generator Disclosure Reports, TR Auction Results
Effective Date: |
Chapter 4, sections 7.3.3, 7.3.4, Ch 8 sections 4.16.1, 4.16.2, 4.16.3 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by April 8, 2010, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00352 - Settlement Aggregation
Effective Date: Dec 15, 2009 |
Chapters 7, 9 |
Amendment Submission Q00
The Technical Panel requests that stakeholders review the amendment submission, as well as the list of outstanding issues, and provide comments by January 22, 2009 using the written submission form. The Panel is particularly interested in comments regarding whether or not there are any unidentified ‘outstanding issues’ that should be considered by the Panel during its review of MR-00352. |
Written Submissions
Hydro One |
On December 15, 2009 the Technical Panel determined that market rule amendment MR-00352 no longer warrants consideration. This amendment is now closed. |
MR-00350 - Forecasts and Assessments - Change Frequency of Publishing 18-Month Outlook
Effective Date: |
Chapter 5 |
Amendment Submission Q00 |
On February 24, 2009, the Technical Panel unanimously determined that market rule amendment submission MR-00350-Q00 no longer warrants consideration. The Panel unanimously approved the IESO's recommendation that based on stakeholder feedback and discussion the market is better served by maintaining the quarterly publication rather than the suggested change to semi-annual publication. The amendment is now closed. |
MR-00347 - Settlements - Linked Wheel Transaction Non-Energy Market Charges
Effective Date: |
Chapter 9 |
Amendment Submission Q00
The Technical Panel requests stakeholders to review and provide written comment on the amendment submission by September 11, 2008 using the written submission form. In addition to any general comments on the submission, the Panel is particularly interested in stakeholder feedback on the Technical Panel comments listed in Part 5 of the amendment submission and the issues/questions listed in Attachment A of the submission. Are there any additional issues or questions that should be answered? Do stakeholders have any views on or responses to the issues and questions identified by the Panel? |
Written Submissions
Transalta
AMPCO |
On December 16, 2008, the Technical Panel determined that market rule amendment MR-00347 no longer warrants consideration. This amendment is now closed. |
MR-00346 - Demand Response - Eliminate Hour-Ahead Dispatchable Load Program
Effective Date: Dec 10, 2008 |
Chapters 3, 7, 9, 11 |
Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R03
The Technical Panel has conditionally recommended the amendment proposal to the IESO Board for approval, subject to no issues being identified by stakeholders regarding the proposal. Panel requests that stakeholders review the amendment submission and amendment proposal, and provide comments to the Panel by September 4th, 2008 using the written submission form. |
IESO Board Decision |
MR-00345 - Reliability - Align Market Rule Definitions of Reliability Related Terms with Bill 44
Effective Date: Jul 18, 2008 |
Chapter 11 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the amendment submission and draft amendment proposal, including the concerns of the Panel transmitter representative summarized in Part 5 of the submission and Attachment B of the proposal, and provide comments by June 5, 2008 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00344 - Minor Amendment Omnibus 2008
Effective Date: Sep 10, 2008 |
Various Chapters |
Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00343 - Market Administration - Clarify Recourse Mechanisms for Market Manuals
Effective Date: Dec 10, 2008 |
Chapter 3 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by May 22, 2008 using the written submission form. |
Written Submission: Hydro One Networks |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision |
MR-00342 - Revenue Meter - Toronto High Voltage Revenue Metering
Effective Date: Sep 10, 2008 |
Chapter 6 |
Amendment Submission Q00 |
Amendment Proposal R00-R03
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by May 22, 2008 using the written submission form.
The Technical Panel is particularly seeking stakeholder feedback on whether the proposed amendment is consistent with Schedule F of the existing OEB Uniform Transmission Rate Order. Panel members interpret Schedule F to imply (i) one revenue meter for each transmission delivery point and (ii) the IESO has some responsibility for the accuracy of the information provided to determine transmission charges and therefore the accuracy of the load diversity adjustment. The proposed amendment would have one revenue meter for more than one transmission delivery point. The draft amendment does not address ensuring the accuracy of the load diversity adjustment as the IESO believes that the OEB has that regulatory oversight. The existing OEB Uniform Transmission Rate Order can be found on the OEB web site at the following location:
www.oeb.gov.on.ca/documents/cases/EB-2007-0759/Uniform_TX_Rates_Order_20071017.pdf. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision |
MR-00341 - Enforcement - Incorporation of Compliance Sanctioning Guidelines into the Market Rules
Effective Date: Sep 10, 2008 |
Chapter 3 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by May 22, 2008 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00340 - Administration - Market Rules Content Policy
Effective Date: |
Chapter 1 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by December 20, 2007 using the written submission form. |
Written Submissions
Hydro One |
On March 18, 2008, the Technical Panel determined that market rule amendment MR-00340 no longer warrants consideration. This amendment is now closed. |
MR-00339 - Revenue Metering - Temporary No-Load Energization of Facilities without Registered Metering Installation
Effective Date: Jun 3, 2009 |
Chapter 9 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by December 11, 2008 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00337 - Administration - Improving Dispute Resolution Process Efficiency and Flexibility
Effective Date: Jun 4, 2008 |
Chapter 3 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by November 29, 2007 using the written submission form. |
Written Submissions
Ontario Power Generation |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00336 - Settlements - Treatment of the Smart Metering Administration Charge
Effective Date: Dec 12, 2007 |
Chapter 9 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the amendment submission and draft amendment proposal and provide comments by September 13, 2007 using the written submission form. |
Amendment Proposal R00-R01
The Technical Panel requests that stakeholders review the draft proposal and provide written comments to the Panel by Thursday October 11, 2007 using the written submission form. |
Amendment Question and Answer Document |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IESO Board Decision |
MR-00335 - Market Administration - Revisions to the Suspension, Termination and Disconnection Provisions for Events of Default
Effective Date: Jun 4, 2008 |
Chapter 3 |
Amendment Submission Q00 |
Amendment Proposal R00-05
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments by November 29, 2007 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IESO Board Decision |
MR-00334 - Emergency Preparedness and System Restoration - Align Restoration Related Market Rules with Industry Practice
Effective Date: Sep 12, 2007 |
Chapters 5 and 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R01
The Technical Panel requests that stakeholders review the amendment submission and draft proposal and provide written comments to the Panel by Thursday May 24, 2007 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision |
MR-00333 - Operating Reserve - Permitting Dispatchable Load Facilities to Supply 10-Minute Synchronized Operating Reserve
Effective Date: Mar 5, 2008 |
Chapter 5 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft proposal and provide written comments to the Panel by Thursday October 11, 2007 using the written submission form.
In addition to comments on the draft proposal, the Panel requests comments in regards to whether or not boundary entities should be permitted to provide 10-minute synchronized operating reserve. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00332 - Operating Reserve (OR) - Reducing Synchronized OR Requirement due to Regional Reserve Sharing Program Changes
Effective Date: Dec 12, 2007 |
Chapter 5 |
Amendment Submission Q00 |
Amendment Proposal R00 and Cost-Benefit Analysis
The Technical Panel requests that stakeholders review the amendment proposal and draft cost-benefit analysis and provide written comment to the Panel by July 5, 2007 using the written submission form. With respect to the draft cost-benefit analysis, the Panel is particularly interested in comments regarding (i) the substance and findings of the analysis, and (ii) the general format and presentation of the analysis as a possible template for future cost-benefit analyses |
Amendment Proposal R00 and Cost-Benefit Analysis
The Technical Panel requests that stakeholders review the amendment proposal and draft cost-benefit analysis and provide written comment to the Panel by July 12, 2007 using the written submission form. With respect to the draft cost-benefit analysis, the Panel is particularly interested in comments regarding (i) the substance and findings of the analysis, and (ii) the general format and presentation of the analysis as a possible template for future cost-benefit analyses.
Cost-Benefit Analysis Showing Tracked Changes This version of the draft cost-benefit analysis shows changes tracked from the version reviewed by the Market Pricing Working Group and the Technical Panel in June 2007.
|
Written Submissions
TransCanada
OPG
APPrO
Econalysis
|
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00331 - Specify the Facility Capability in the Market Schedule
Effective Date: Sep 12, 2007 |
Appendix 7.5 |
Amendment Proposal R00
The IESO Board requests that persons wishing to submit written comments on the proposed amendment do so by January 12, 2007 using the written submission form. |
Written Submissions
AMPCO
APPrO
Ontario Power Generation
TransCanada Energy
TransAlta Energy Marketing
|
IESO Board Decision |
MR-00330 - Reliability Standards - Mapping Reliability Standards to Ontario Market Participants
Effective Date: Sep 12, 2007 |
Chapter 5 |
Amendment Submission Q00 |
Amendment Proposal R00-R04
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments to the Panel by April 19, 2007 using the written submission form.
Written Submissions
Hydro One Networks
|
Technical Panel Recommendation on MR-00330-R00-R04. |
IESO Board Decision |
IESO Board Decision |
MR-00329 - Ancillary Services – Eliminate Requirement for Minimum Amount of Regulation/Automatic Generation Control
Effective Date: Oct 20, 2009 |
Chapter 5 |
Amendment Submission Q00 The Technical Panel requests that stakeholders review this amendment submission and provide comments to the Technical Panel by November 30, 2006, using the written submission form. |
Written Submissions
OPG |
Amendment Proposal R00 |
On October 20, 2009 the Technical Panel determined that market rule amendment MR-00329 no longer warrants consideration. This amendment is now closed. |
MR-00328 - Duration of Reliability Must Run Contracts
Effective Date: |
Chapter 7 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments to the Panel by September 28, 2006 using the written submission form. |
The Technical Panel did not recommend this amendment to the IESO Board and the IESO withdraw the proposal. This amendment is now closed. |
MR-00327 - Dispatch Data Submissions - Allow Price Changes Inside the Mandatory Window
Effective Date: Mar 7, 2007 |
Chapter 7 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments to the Panel by January 10, 2007 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision |
MR-00326 - Review of New Reliability Standards
Effective Date: |
Chapter 5 |
Amendment Submission Q00 In addition to general comments on the amendment submission, the Technical Panel is seeking stakeholder comments on specific questions documented in Part 5 of the amendment submission under the heading "Technical Panel Comments". Stakeholders are requested to provide comments by February 8, 2007, using the written submission form.
Written Submissions
Ontario Power Generation
Hydro One Networks |
On June 10, 2008, the Technical Panel unanimously determined that market rule amendment submission MR-00326-Q00 no longer warrants consideration. This amendment is now closed. |
MR-00325 - Duration of Contracted Ancillary Services Contracts
Effective Date: Dec 12, 2006 |
Chapter 7 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the amendment submission and the draft amendment proposal and provide comments to the Panel by September 28, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal ROO |
IESO Board Decision R00 |
MR-00324 - Clean-up of Rule Notes and Definitions
Effective Date: Dec 6, 2006 |
Chapter 5, 8, 9, 11 |
Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00-R01 |
MR-00321 - Connection Assessment - Change Connection Assessment Requirements for Embedded Generation
Effective Date: Sep 13, 2006 |
Chapter 11 |
Amendment Submission Q00 |
Amendment Proposal R00
The Technical Panel requests that stakeholders review the amendment submission and draft amendment proposal and provide written comment to the Panel using the written submission form by July 12, 2006. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision ROO |
MR-00320 - Designated Program Market Participant
Effective Date: Jul 1, 2006 |
Chapters 2 and 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R01 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by May 17, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00319 - Interim Reporting of Real-Time Intertie Transaction Failure Charges on Preliminary Settlement Statements
Effective Date: Jun 1, 2006 |
Chapter 9 |
Amendment Submission Q00 |
Amendment Proposal R00 The Technical Panel requests that stakeholders review both the amendment submission and the amendment proposal and provide comments to the Technical Panel by April 27, 2006 using the written submission form. |
Written Comments
MEHQ
Coral Energy Canada
|
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00318 - Day-Ahead Commitment Process - Temporary Extension to Notice of Disagreement (NoD) Window
Effective Date: May 31, 2006 |
Chapter 9, section 6 |
Amendment Submission Q00 |
Amendment Proposal R00-R01 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by April 26, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IESO Board Decision R00-R01 |
MR-00317 - Day-Ahead Commitment Process - Prohibit Import Eligible for DA-IOG to Be Part of a Linked Wheeling Through Transaction
Effective Date: May 31, 2006 |
Chapters 7 and 9 |
Amendment Submission Q00 |
Amendment Proposal R00-R02 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by April 26, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision R00-R02 |
MR-00316 - Day-Ahead Commitment Process - Minimum Generation Block Run-time
Effective Date: May 31, 2006 |
Chapters 7 and 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R03 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by April 26, 2006 using the written submission form. |
Written Submissions OPG |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00314 - IESO Authorities and Obligations to Cancel DACP due to Software or Process Failures
Effective Date: May 31, 2006 |
Chapter 7 |
Amendment Submission Q00 |
Amendment Proposal R00 The Technical Panel requests that stakeholders review both the amendment submission and the amendment proposal and provide comments to the Technical Panel by March 22, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00313 - Account for Congestion Management Settlement Credit Payments in the Determination of Day-Ahead Intertie Offer Guarantee
Effective Date: May 31, 2006 |
Chapter 9, section 3.8A |
Amendment Submission Q00 |
Amendment Proposal R00 The Technical Panel requests stakeholders review the draft amendment proposal and provide comments to the Panel by March 1, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00312 - Revenue Metering: Relief to Retain Registration Under the Alternative Metering Standard
Effective Date: Dec 12, 2006 |
Chapter 6 Section 4.4 and Appendix 6.2 |
Amendment Submission Q00 |
Amendment Proposal R00-R02 The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments to the Panel by October 25, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision R00-R02 |
MR-00311 - Reliability - Emergency Load Reduction Program
Effective Date: Jun 15, 2006 |
Chapters 7 and 9 |
Amendment Submission Q00 The Technical Panel requests that stakeholders review this amendment submission and provides comments to the Technical Panel by March 1, 2006, using the written submission form. |
Written Submissions
OPG |
Amendment Proposal R00-R02 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by March 22, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00310 - Day-Ahead Commitment Process - IESO Authorities and Obligations Regarding Time Period in Which the DACP is Functioning and DACP Sunset
Effective Date: May 31, 2006 |
Chapter 7 |
Amendment Proposal R00 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by January 6, 2006 using the written submission form.
Written Submissions
OPG |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00308 - Settlement Charges for Intertie Transaction Failures
Effective Date: Jun 1, 2006 |
Chapters 3, 7 and 9 |
Amendment Submission Q00 |
Amendment Proposal R00-R04 The Technical Panel requests that stakeholders review the amendment proposal and provide comments to the Technical Panel by January 23, 2006 using the written submission form. |
Written Submissions
Manitoba Hydro
Coral Energy Canada
OPG
Powerex Corp |
Technical Panel Recommendation on Amendment Proposal R00-R04 |
IESO Board Decision R00-R04 |
MR-00307 - Forecasts and Assessments - Align Market Rules with IESO's Obligations Under the Electricity Act, 1998
Effective Date: Mar 8, 2006 |
Chapter 5, section 7 and Chapter 10, sections 7-9. |
Amendment Submission Q00 The Technical Panel requests that stakeholders review the amendment submission and provide comments to the Technical Panel by January 20, 2006 using the written submission form. |
Amendment Proposal R00-R05 The Technical Panel requests that stakeholders review the amendment proposal and provide comments to the Technical Panel by January 20, 2006 using the written submission form. |
Written Submissions
Bruce Power
Hydro One
OPG |
Technical Panel Recommendation on Amendment Proposal R00-R06 |
IESO Board Decision R00-R06 |
MR-00306 - Constrained Off CMSC Payments in Designated Watch Zones
Effective Date: Jul 1, 2006 |
Appendix 7.6 |
Amendment Submission Q00 |
Amendment Proposal R00-R01 version 2.0 The Technical Panel requests that stakeholders review the amendment proposal and provide comments to the Technical Panel by March 1, 2006 using the written submission form. |
Written Submissions
Manitoba Hydro
TransAlta
Hydro Quebec
Powerex Corp
OPG |
Amendment Proposal R00-R02 version 4.0 The Technical Panel requests that stakeholders review the amendment proposal and provide comments to the Technical Panel by May 12, 2006 using the written submission form. |
Written Submissions
Manitoba Hydro
Powerex Corp |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision R00-R02 |
MR-00305 - Day-Ahead Commitment Process - Reliability Guarantees (Settlement of the Day-Ahead Commitment Process)
Effective Date: May 31, 2006 |
Chapter 9 |
Amendment Submission Q00 |
Amendment Proposal R00-R09 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by January 6, 2006 using the written submission form.
Written Submissions
OPG |
Technical Panel Recommendation on Amendment Proposal R00-R09 |
IESO Board Decision R00-R09 |
MR-00304 - Day-Ahead Commitment Process - Pre-Dispatch Scheduling and Commitment
Effective Date: May 31, 2006 |
Chapter 7 |
Amendment Submission Q00 |
Amendment Proposal R00 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by January 6, 2006 using the written submission form.
Written Submissions
OPG |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00303 - Day-Ahead Commitment Processes - Data Submission
Effective Date: May 31, 2006 |
Chapter 7, section 2.2; Appendix 7.7, section 1.3.3 |
Amendment Submission Q00 |
Amendment Proposal R00-R05 The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by January 6, 2006 using the written submission form.
Written Submissions
OPG |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IESO Board Decision R00-R05 |
MR-00301 - Settlements - Aggregating Contracted Ancillary Services Settlement Information
Effective Date: |
Chapter 9, section 6.5 |
Amendment Submission Q00
|
On July 24, 2007, the Technical Panel unanimously determined that market rule amendment submission MR-00301-Q00 no longer warrants consideration. This amendment is now closed. |
MR-00299 - Operating Reserve Requirements - Regional Reserve Sharing
Effective Date: Dec 14, 2005 |
Chapter 5, section 4.5 |
Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by October 20, 2005 using the written submission form.
The market rules are not intended to specify limits that are contained in reliability organization standards and programs. Following this principle, the proposed amendment would not specify any limits but rather refer to the applicable reliability standard.
Six Technical Panel members support the draft proposal (as posted) which specifies a contribution of up to 100 MW that the IESO may count as operating reserve from other participating control areas because:
The NPCC design basis is 100 MW,
The market impacts of a 100 MW reduction in the demand for domestic operating reserve have been quantified (see draft proposal), and
An increase from 50 MW to 100 MW would require NPCC approval and this approval would only be granted on the basis that reliability would be maintained.
Five Technical Panel members assert that the amendment should specify a 50 MW limit. This assertion is made on the basis that:
The NPCC procedure document currently specifies a 50 MW limit,
The market impacts of a 50 MW reduction in the demand for domestic operating reserve have been quantified (see draft proposal), and
Any increase in the limit should be stakeholdered through the market rule amendment process.
In addition to general comments on the draft proposal, the Technical Panel is seeking stakeholder comments on whether no limit, a 50 MW limit, or a 100 MW limit is appropriate for this market rule amendment.
Written Submissions
Wescast
OPG |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00298 - Market Pricing - Emergency Control Actions and Counter-Intuitive Prices – Administrative Pricing
Effective Date: Aug 12, 2005 |
Chapter 7, section 8.4A |
IESO Board Decision R00 |
MR-00296 - Market Pricing - Emergency Control Actions and Counter-Intuitive Prices - Inputs to Dispatch Scheduling and Pricing Process
Effective Date: Aug 12, 2005 |
Appendix 7.5, section 3.2 |
Amendment Submission Q00 The Technical Panel requests that stakeholders review this amendment submission and provide comments to the Technical Panel by June 7, 2005 using the written submission form.
Written Submissions Bruce Power Ivaco Wescast Gerdau Ameristeel |
Amendment Proposal R00-R01 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by June 14, 2005 using the written submission form.
Written Submissions OPG Falconbridge Wescast Safety Power |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IESO Board Decision R00 |
MR-00295 - Clarify Local Market Power Mitigation
Effective Date: Oct 19, 2005 |
Appendix 7.6 |
Amendment Submission Q00 |
Amendment Proposal R00 Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 18, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00294 - Energy Estimate Allowed Based on Energy Metering Not Necessarily Complying With the Registered Wholesale Revenue Metering Standard
Effective Date: Mar 8, 2006 |
Chapter 9, section 2.1A.2 |
Amendment Submission Q00 Note: This market rule amendment submission has been withdrawn by its submitter, Hydro One Networks. |
MR-00293 - Transmission Equipment Thermal Ratings
Effective Date: Sep 13, 2006 |
Chapter 4, Appendix 4.4, 4.5A, 4.9; Chapter 5, section 5.2 |
Amendment Submission Q00 |
Amendment Proposal R00-R03 The Technical Panel requests that stakeholders review the amendment proposal and provide comments to the Technical Panel by March 1, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00292 - Additional Compensation for Dispatchable Loads under Administrative Pricing
Effective Date: Dec 7, 2005 |
Chapter 7, section 8.4A |
Amendment Submission Q00 |
Amendment Proposal R00 Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 18, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00291 - Settlements - Adjustment Period Allocation
Effective Date: Dec 7, 2005 |
Chapter 2, section 9; Chapter 9, section 6; Chapter 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R03 Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 18, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00290 - Align Market Rules with OEB-IESO Protocol on Market Surveillance Panel
Effective Date: Sep 14, 2005 |
Chapter 3, section 4; Chapter 7, sections 2, 3, 5, 7, 9, Appendix 7.6, 7.7 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel requests that stakeholders review this amendment submission and submit comments to the Panel by April 12, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00289 - 14-Day Advance Outage Approval
Effective Date: Dec 7, 2005 |
Chapter 5, section 6; Chapter 11 |
Amendment Submission Q00 |
Amendment Proposal R00-R05 Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by July 18, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R06 |
IESO Board Decision R00-R06 |
MR-00288 - Reactive Power Requirements for Induction Generation Units
Effective Date: Sep 14, 2005 |
Chapter 4, Appendix 4.2 |
Amendment Submission Q00 |
Amendment Proposal R00 – Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by May 9, 2005, using the written submission form.
Written Submissions
TransAlta
AMEC |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00285 - Bill 100 Consequential Amendments
Effective Date: Jan 1, 2005 |
Chapter 1, section 5, 7 and 14; Chapter 3, sections 1, 2, 3, 4 and 5; Chapter 9, section 1; and Chapter 11 |
Amendment Proposal R00-R05 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by November 26, 2004, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IMO-Board Decision R00-R05 |
MR-00284 - Compliance - Include Reliability Impact as Criterion for Determining Financial Penalties
Effective Date: Mar 7, 2007 |
Chapter 3 (6.6.7, 6.6.13); Chapter 5 (11.8.1) |
Amendment Submission Q00 |
Amendment Proposal R00-R02
The Technical Panel requests that stakeholders review the draft amendment proposal and provide comments to the Panel by October 5, 2006 using the written submission form.
Written Submissions
Horizon Utilities
Hydro One
OPG
TransAlta |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision R00-R02 |
MR-00282 - Changes to Emergency Preparedness Market Rules
Effective Date: Jan 1, 2005 |
Chapter 5, section 11; Chapter 1, sections 4 and 13 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R05 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review the draft amendment proposal and submit any comments to the Panel by November 12, 2004 using the Written Submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IMO-Board Decision R00-R05 |
MR-00280 - Prudential Requirements - Limit Use of Cash to Meet Prudential Support Obligation
Effective Date: Nov 4, 2004 |
Chapter 2, section 5.7.2 |
Technical Panel Determination on Amendment Submission |
Amendment Proposal R00 - Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by September 16, 2004, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decisions R00 |
MR-00279 - Revenue Metering - Revenue Metering Installations Whose Registration Expires at the End of 2004
Effective Date: Dec 8, 2004 |
Chapter 6 various sections |
Technical Panel Determination on Admendment Submission Q00 |
Amendment Proposal R00-R06 - Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by September 16, 2004, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R06 |
IMO Board Decision R00-R06 |
MR-00263 - Correct Non-Material Discrepancies in Dispatch Scheduling Algorithm Description
Effective Date: Sep 14, 2005 |
Chapter 7, Appendix 7.5 , sections 2.4.5, 6.7.1 and 7.6.1 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision R00-R03 |
MR-00262 - Settlements - Settlement Statement Re-Calculation
Effective Date: Dec 8, 2004 |
Chapter 9, section 6.8 |
Technical Panel Determination on Admendment Submission Q00 |
Amendment Proposal R00-R02 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by September 20, 2004, using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IMO Board Decision R00-R02 |
MR-00261 - Technical and Metering Requirements for Small Embedded Facilities
Effective Date: Sep 14, 2005 |
Chapter 4 Appendices; Chapter 6 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R06 - Technical Panel Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft amendment proposal and provide any comments to the Technical Panel by February 21, 2005, using the written submission form.
Written Submissions
Comments from Brantford Power |
Technical Panel Recommendation on Amendment Proposal R00-R06 |
IESO Board Decision R00-R06 |
MR-00260 - Spare Generation On-Line Minimum Run-Time
Effective Date: Oct 6, 2004 |
Chapter 11 |
Technical Panel Determination on Amendment Submission Q00 The The Technical Panel requests that stakeholders review this amendment submission and provide any comments to the Panel using the written submission form by May 19, 2004. |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO-Board Decision R00 |
MR-00259 - Impact of New Limitations Act
Effective Date: Sep 1, 2004 |
Chapter 3, section 2.4.2, subsections 2.4.2.1 and 2.4.2.2 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R01 - Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft market rule amendment proposal and provide comments on the proposal to the
Panel by June 17, 2004 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-01 |
IMO-Board Decision R00 |
MR-00258 - Testing Requirements for Revenue Metering Requirements
Effective Date: Dec 8, 2004 |
Chapter 6, section 11.1.3.3a and App. 6.3, sections 1.4 and 1.5 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R01 - Request for Stakeholder Review and Comment. The Technical Panel reviewed MR-00258-R00-01 at its July 13, 2004 meeting and requests comments before August 4, 2004 using the written submission form from market participants regarding the issue whether or not the requirement for routine IT checks should differentiate between capacitor voltage transformers (CVTs) and conventional electromagnetic voltage transformers (VTs).
Written Submissions Comments from Toronto Hydro Electric-System Ltd |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IMO Board Decisions R00-R01 |
MR-00257 - Prudential Requirements - Form of Pledge of Cash or Cash Equivalent
Effective Date: Jul 6, 2004 |
Chapter 2, Section 5.7.5.2 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel requests that stakeholders review this amendment submission and to provide comments to the Technical Panel by May 3, 2004 on the amendment submission using the written submission form. The “Pledge of Cash and Treasury Bills” referenced in the amendment submission can be found at the following location http://www.theimo.com/imoweb/pubs/settlements/se_PledgeOfCashTreasuryBills.doc. |
Technical Panel Recommendation on
Amendment Proposal R00 |
IMO-Board Decision R00 |
MR-00256 - Transitional Demand Response Program
Effective Date: Apr 20, 2004 |
Chapter 7, Section 14; Chapter 9, Section 4.7c, 4.8.1.10 and 4.8.2.5 |
Technical Panel Recommendation on Amendment Proposal R00-02 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review the recommended proposal and provide written comment, using the written submission form by March 22, 2004. The IMO Board will be considering the recommended proposal at its meeting on March 26, 2004, along with any written stakeholder comments received. |
IMO Board Decision R00-R02 A revised IMO Board approved market rule amendment has replaced the previous document. The previous document had an error in the section numbering within MR-00256-R02. There has been no other change to the approved rule amendment. We apologise for any confusion or inconvenience this error may caused. |
MR-00255 - Extension of Emergency Demand Response Program
Effective Date: May 1, 2004 |
Chapter 5 section 4.8A |
Technical Panel Recommendation on Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests stakeholders to review the recommended proposal and provide written comment, using the Written Submission form by March 19, 2004. The IMO Board will be considering the recommended proposal at its meeting on March 26, 2004, along with any written stakeholder comments received. |
IMO Board Decision R00 |
MR-00254 - Allocation of IMO Adjustment Account
Effective Date: Apr 20, 2004 |
Chapter 9, Section 6.18 |
Amendment Proposal R00 - The IMO Board is considering market rule amendments regarding the allocation of the IMO adjustment account - MR-00254-R00. The proposed changes would allow the IMO Board to allocate excess funds from this account to special projects rather than, as currently prescribed in the market rules, using excess funds to reduce the IMO administration fee. Interested persons are requested to review and provide comments to the IMO Board on the amendment proposal by February 5, 2004, using the written submission form . The IMO Board will be considering the proposal and any comments received at its meeting on February 13, 2004. The Technical Panel will also be reviewing this amendment proposal at its meeting on February 3, 2004. |
IMO Board Decision R00 |
MR-00253 - Review of Administered Pricing
Effective Date: Jul 26, 2004 |
Chapter 7, Section 8.4 and 13 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel invites stakeholders to review and provide comments on the amendment submission, including the Technical Panel comments noted in Part 5 of the submission, and the strawman discussion paper by Monday March 1, 2004, using the written submission form.
Written Submissions Comments from Brascan Comments from Dofasco Comments from Bruce Power Comments from TransCanada Energy |
Amendment Proposal R00 - R02 Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft market rule amendment proposal and provide comments on the proposal to the Panel by May 11, 2004 using the written submission form . Comments received from stakeholders responding to an earlier posted draft rule amendment proposal will be considered along with any additional comments received with this posting. |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IMO-Board Decision R00-R02 |
MR-00250 - Transmission Customers - Metering Requirements for Embedded Generation Facilities
Effective Date: Jun 2, 2004 |
Chapter 6, Sections 2 and 4 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by March 5, 2004 using the written submission form.
Written Submissions Comments from Toromont Comments from Brantford Hydro |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00249 - Extension of Registration of Metering Installations Granted Temporary Dispensation by Measurement Canada
Effective Date: Dec 17, 2003 |
Chapter 6 and App 6.1 & 6.2 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R02 - Request for Stakeholder Review and Comment In its review and recommendation of these amendment proposals, the Technical Panel expressed concern over two issues. The first issue is the treatment of metered market participant non-compliance with respect to the obligations that will remain upon seal expiry for their metering installations. The second issues is with respect to the market’s need for assurance that the eligible metering installations to which the temporary dispensation applies will be adequately maintained and provide accurate data for settlement purposes. The IMO will be working with metered market participants and metering service providers over the next few weeks to address these issues, and additional information may be posted on these issues.
The Panel requests that stakeholders review these recommended rule amendments, and in particular on the issues noted above, and to provide written comment by Friday November 21, 2003, using the Written Submission form. Any written submissions received will be provided to the IMO Board for consideration in its decision regarding MR-00249. The IMO Board will be meeting on November 24, 2003 to consider this recommended amendment. |
Related Documents
Letter from Measurement Canada List of Metering Installations Covered by Temporary Dispensation |
IMO Board Decision R00-R02 |
MR-00248 - Rule Amendments Consequential to IMO Permanent Licence and Amendments to the OEB Act
Effective Date: Dec 8, 2004 |
various chapters |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R02 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by August 12, 2004 using the written submission form. |
Techncial Panel Recommendation on Amendment Proposal R00-R02 |
IMO Board Decision R00-R02 |
MR-00247 - Amendments to Ensure Proper Operation and Compensation for Special Protection Systems
Effective Date: Mar 8, 2006 |
Chapter 5, Sections 8.2 and 8.3 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel invites written comments using the written submission form by December 19, 2003. |
Amendment Proposal R00-R02 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by May 19, 2004 using the written submission form.
Written Submissions Comments from Bruce Power Comments from Hamilton Hydro Comments from HydroOne |
Amendment Proposal R00-R02 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by October 27, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IESO Board Decision R00-R02 |
MR-00246 - Multi-Interval Optimization - Changes to Dispatch Algorithm
Effective Date: Jun 23, 2004 |
Chapter 7, App. 7.5, Sections 1.1, (App. 7) 2.2, 2.3, 2.11, 4.2, 4.10, 5.1, 6.1, 6.5, 7.6 (App. 7.5) |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal - R00-R07 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by February 24, 2004 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R07 |
IMO Board Decision R00-R07 |
MR-00245 - Multi-Interval Optimization - Permissions and Obligations
Effective Date: Jun 23, 2004 |
Chapters 7and 11 App 7.1, Sections 2.2.6A (new), 7.1A |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal - R00-R03 - Request for Stakeholder Review and Comment
The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by February 24, 2004 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IMO Board Decision R00-R03 |
MR-00244 - Generator Excitation System Performance Requirements
Effective Date: Dec 8, 2004 |
Appendix: 4.2 Sections: 12 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by August 18, 2004 using the written submission form. |
IMO Board Decision R00 |
MR-00242 - Management of Transmission Rights Clearing Account Minimum Reserve Level
Effective Date: Jan 6, 2004 |
Chapter 8, Sections: 4.18 & 4.19 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel invites written comments using the written submission form by September 22, 2003. |
Technical Panel Recommendation on Amendment Proposal R00-R04 |
IMO Board Decision R00-R04 |
MR-00241 - Treatment of Enhanced Combined Cycle Generation Facilities
Effective Date: Mar 3, 2004 |
Chapter 7 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R01 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by November 3, 2003 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IMO Board Decision R00-R01 |
MR-00240 - MR-00240 - Segregated Mode of Operation - Dispatch Data and Request Timing
Effective Date: Apr 20, 2004 |
Appendix 7.7 , sections 1.2 and 1.3 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by February 19, 2004 using the written submission form.. |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00237 - Functional Deferral 6 - Adjusting Dispatch Instructions to the Defined Metering Point
Effective Date: Jul 26, 2003 |
Chapter 9, Sections 3.1.4A.1 and 3.1.4A.2 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 Attachment A |
MR-00235 - Market Incentives to Increase Spare Generation On-Line/Including Control Action Sources of Operating Reserve in the Market
Effective Date: Aug 6, 2003 |
Chapter 5, Section 4.5.6A; Chapter 7, Section 2.2B (new), 5.7 (new), 6.3A (new); Chapter 9, Section 4.7B (new); and Chapter 11 |
Amendment Proposal - Request for Stakeholder Review and Comment - R00-R05 The Technical Panel invites comment on this draft market rule amendment proposal by June 23, 2003. It is particularly interested in comments regarding the following: 1) Spare Generation On-Line (MR-235-R00-04)- Are the proposed cost guarantees sufficient to cover all incremental costs borne by a generator in starting-up and operating at its minimum loading point for its minimum run-time? (4.7B)
- Should the submission of inaccurate cost data be deemed to be a breach of the market rules or should inappropiate payments based on inaccurate cost data be automatically clawed back by the IMO? (2.2B.2)
2) Control Action Sources of Operating Reserve in the Market (MR-00235-R05)- Should the market rules specify the criteria by which the IMO Board would set the control action OR prices?
- Should there be a periodic control action OR price review mechanism included in the market rules?
|
IMO Board Decision R00-R05 |
MR-00234 - Revised Operating Reserve Restoration Standards
Effective Date: Jul 26, 2003 |
Chapter 5, Sections 4.5.10, 4.5.21 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel invites comment on this proposal by June 21, 2003. |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00232 - Allow Unrestricted Revisions to Dispatch Data up to 2 Hours Ahead of Dispatch Hour
Effective Date: Sep 27, 2003 |
Chapter 7, Sections 3.3.3, 3.3.4 and 3.3.6 |
Technical Panel Determination on Amendment Submission |
Technical Panel Recommendation on Amendment Proposal R00 The Technical Panel requests that any person wishing to provide comments on this recommended market rule amendment proposal, to please do so by June 4, 2003 using the written submission form. The recommended market rule amendment proposal and any written submissions received will be considered by the IMO Board at its meeting on June 5, 2003. |
Technical Panel Recommendation on Revised Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00230 - Disclosure of Generator Output and Outage Information and Interchange Schedules and Actual Flows on an Intertie Zone Basis
Effective Date: Dec 31, 2003 |
Chapter 4, Section 7.3.4; Chapter 5, Section 6.5.5; and Chapter 9, Section 2.5.3 |
IMO Board Decision R00 More information about this amendment is available on the Consultation on Proposed Changes to IMO Information Confidentiality Catalogue page. |
MR-00228 - Metering Installations - Seal Expiry Requirements
Effective Date: Jun 4, 2003 |
Chapter 6, Appendix 6.2 |
Technical Panel Determination on Amendment Submission |
Technical Panel Recommendation on Amendment Proposal |
IMO Board Decision R00-R03 |
MR-00227 - Change Market Rule Requirements for Auditing of Dispatch Algorithm and Settlement Processes and Procedures
Effective Date: Jun 4, 2003 |
Chapter 7, Section 4.2.4 Chapter 9, Section 6.17 |
Technical Panel Determination on Amendment Submission The Technical Panel invites written comments on the suggested changes and related issues identified in the amendment submission. Stakeholders wishing to provide comments are requested to do so using the written submission form by March 31, 2003. |
Technical Panel Recommendation on Amendment Proposal |
IMO Board Decision R00-R01 |
MR-00225 - Clarifying Transmitter's Role to Coordinate Outages with Impacted Market Participants
Effective Date: Nov 23, 2003 |
Chapter 5, Section 1.2.2 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal - Request for Stakeholder Review and Comment R00-R01 The Technical Panel invites written comments using the written submission form by September 22, 2003. |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IMO Board Decision R00-R01 |
MR-00224 - Replace Requirement for Settlement Reserve Account
Effective Date: Nov 23, 2003 |
Chapters 2, 9 & 11 Sections 8.7.1.2 (ch.2), 6.11.5, 6.14.4.2, 6.14.6, 6.14.7,6.15.7, 6.18.5, 6.18.5.1 (ch.9) |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IMO Board Decision R00-R05 |
MR-00223 - Transmission Rights Participation Requirements and Sub-Auctions
Effective Date: Jun 12, 2003 |
Chapter 8, Sections 4.8.3 and 4.11.4 |
Technical Panel Determination on Amendment Submission |
Technical Panel Recommendation on Amendment Proposal R00-R02 The Technical Panel invites comment on this recommended market rule amendment proposal by June 4, 2003. The recommended market rule amendment proposal and any written submissions received will be considered by the IMO Board at its meeting on June 5, 2003. |
IMO Board Decision R00-R02 |
MR-00222 - Extending Deferral of Capacity Reserve Market
Effective Date: Jun 4, 2003 |
Chapter 1, Section 4.4A |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00221 - Extension of the Emergency Demand Response Program
Effective Date: May 1, 2003 |
Chapter 5, Section 4.8A |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 This amendment will come into force on May 1, 2003, to ensure continuity of the Emergency Demand Response Program. |
MR-00220 - Hour-Ahead Dispatchable Loads
Effective Date: Jun 4, 2003 |
Chapter 7 & 9 |
Technical Panel Determination on Amendment Submission Q00 Stakeholders wishing to provide comments on the hour-ahead dispatchable load initiative are requested to provide their comments through the Market Evolution Program forum, which can be found at Market Evolution. |
Amendment Proposal - Request for Stakeholder Review and Comment R00-R16 The Technical Panel invites written comments on the draft amendment proposal. As the proposal is quite lengthy, the Panel recommends that stakeholders review R00 as a priority, as these sections outline the main features of the hour-ahead dispatchable load initiative. Stakeholders wishing to provide comments are requested to do so using the written submission form by Monday April 21, 2003. |
Technical Panel Recommendation on Amendment Proposal |
IMO Board Decision R00-R17 |
MR-00219 - Arranging Replacement Energy to Support Planned Outages
Effective Date: Jun 4, 2003 |
Chapter 5, Sections 6.3.6 - 6.3.10 (new) |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal - Request for Stakeholder Review and Comment R00 The IMO Technical Panel invites comment on this submission by March 14, 2003. It is particularly interested in comments regarding the compliance issues associated with this proposal, including the application of the failed intertie transaction guidelines (section 6.3.7.2) and the use of a formula based penalty for failure to offer (section 6.3.10). |
Written Submissions:
TransCanada Energy Bruce Power |
Technical Panel Recommendation on Amendment Proposal |
IMO Board Decision R00-R01 |
MR-00218 - Extension of Deferral of Treatment of Dispatch Deviation as Increase in Non-Dispatchable Load
Effective Date: Jun 4, 2003 |
Chapter 7, Sections 4.4.3; 6.4.2A; 7.5.5A Appendix 7.5 Sections 7.3.2; 8.4.3 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R04 |
IMO Board Decision R00-R04 |
MR-00217 - Market Rule Amendments to Support IMO Board Process for Hearings
Effective Date: Jun 4, 2003 |
Chapter 3, Sections 5.3.1.5A (new); 5.3.3; 6.3.7C |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal - Request for Stakeholder Review and Comment R00-R01 The IMO Technical Panel invites comment on this proposal by March 10, 2003. |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IMO Board Decision R00-R01 |
MR-00215 - Suspension of Deemed Credit Downgrade Resulting from Credit Watch Warning
Effective Date: Nov 19, 2002 |
Chapter 2, Section 5.8.2 |
MR-00215-R00 |
MR-00214 - Bill 210 Consequential Market Rule Amendments
Effective Date: Dec 13, 2002 |
Chapter 9, Section 1.2 |
MR-00214-R00 |
MR-00213 - Simplifying Connection Assessment Market Rules
Effective Date: Mar 28, 2003 |
Chapter 4, Sections 6.1.1-6.1.23; 6.4.2A; 7.1 |
Technical Panel Determination on Amendment Submission Q00 The IMO Technical Panel invites comment on this submission and related issues, as noted in Part 5 of the amendment submission, by December 23, 2002. |
Written Submissions:
Hydro One Networks Inc TransAlta Energy Corporation |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IMO Board Decision R00-R03 |
MR-00212 - Prudential Support - Revisions to Prudential Support Obligations
Effective Date: Aug 1, 2007 |
Chapter 2 Section 5 |
Electricity Distributors Association Amendment Submission Q00 |
Amendment Submission Q00 |
Amendment Proposal R00-R03 The Technical Panel requests that stakeholders review the amendment submission and draft proposal and provide written comments to the Panel by Friday, June 8, 2007 using the written submission form.
Written Submissions
Hydro One Networks |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IESO Board Decision |
MR-00210 - Energy Offers and Bids & Operating Reserve Offers
Effective Date: Oct 9, 2002 |
Chapter 7, Sections 3.5.3 and 3.6.2 |
Technical Panel Determination on Amendment Submission |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00208 - Remove Deferred Preliminary/Final Pricing Requirements from the Rules
Effective Date: Oct 9, 2002 |
Chapter 7, Sections 3.1, 3.2, 3.3, 4.4, 6.4, 6.5, 8.1. 8.2, and 8.3, Chapter 9, Section 3.8A.1 |
Technical Panel Determination on Amendment Submission Q00 Persons wishing to comment on this amendment submission are asked to make a Market Rule Written Submission, by Friday, September 20, 2002. |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IMO Board Decision R00-R05 |
MR-00207 - Local Market Power Rule Amendments - Pre-Inquiry Adjustment to CMSC Re-calculation
Effective Date: Sep 10, 2002 |
Chapter 7 Section 1.4 and 1.5 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R01 Persons wishing to comment on this amendment submission are asked to make a Market Rule Written Submission, by Friday, September 20, 2002. |
MR-00206 - Clarification of Application of Reliability Must Run Contracting
Effective Date: Mar 5, 2003 |
Chapter 5, Section 4.8; 4.8.1-4.8.3; Chapter 7, Section 9.6; 9.6.1; 9.6.2; 9.6.4-9.6.6; 9.6.8-9.6.10; 9.6.12; Chapter 9, Section 4.2; Chapter 11 (definitions) |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R03 |
IMO Board Decision R00-R03 |
MR-00205 - Alternative Metering Installation Standards - Accuracy Requirements for Instrument Transformers
Effective Date: Oct 9, 2002 |
Chapter 6, Appendix 6.2, Sections 1.7 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00204 - Intertie Offer Guarantee
Effective Date: Aug 1, 2002 |
Chapter 9 sections 3.8A.1, 3.8A.3 to 3.8A.6 (new) and 4.8.2.3 (new) |
MR-00204-R00-R01 |
MR-00203 - Bill 58: Consequential Changes to the Powers of the Market Surveillance Panel
Effective Date: Mar 5, 2003 |
Chapter 3, Sections 3.3.2A; 3.3.3; 3.4.1 A/B; 3.4.2; 3.4.6-3.4.10 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00-R02 |
IMO Board Decision R00-R02 |
MR-00202 - Regulation of Meter Service Providers
Effective Date: Mar 5, 2003 |
Chapter 6, Section 3.2; 5.1.13.2; 5.2.3; 5.3.1.2; 13.1.1.8; Appendix 6.6 |
Technical Panel Determination on Amendment Submission Q00 The IMO Technical Panel invites comment on this submission and related issues, as noted in Part 5 of the amendment submission, by September 6, 2002. |
Written Submissions:
Hydro One Networks Inc Five Nations Energy Inc |
Technical Panel Recommendations on Amendment Proposal:
R00 R01-R02 |
IMO Board Decisions
R00 R01-R02 |
MR-00200 - Proposed Local Market Power Rule Amendments
Effective Date: Sep 10, 2002 |
Chapter 7 & 11(Definitions), Appendix 7.6, Sections 1.3.3, 1.3.4, 1.3.5, 1.3.7, 1.3.8 |
Technical Panel Determination on Amendment Submission Q00 The Technical Panel is inviting market participant and stakeholder comment on MR-00200-Q00. Persons wishing to comment on this amendment submission are asked to make a Market Rule Written Submission, by Wednesday, August 7, 2002. |
Written Submissions on Amendment Submission - Bruce Power |
Technical Panel Recommendation on Amendment Proposal R00 |
MR-00196 - Transmission Rights Market Contingency Plan and Clean Up
Effective Date: Jul 9, 2002 |
Chapter 8, Sections 4.1, 4.8, 4.13 |
Technical Panel Determination on Amendment Submission Q00-Q02 |
Technical Panel Recommendation on Amendment Proposal R00-R03 These recommended rule amendments are being submitted to the IMO Board for approval at its meeting on July 4, 2002. |
Proposed Rule Amendment for Review and Comment R00 |
IMO Board Decision R00-R03 |
MR-00195 - Self Induced Constrained-Off CMSC Payments and Negative Priced Import Offers
Effective Date: Jan 6, 2004 |
Chapter 7, 9 & 11 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00-R05 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to provide comments on the proposal to the Panel by November 24, 2003 using the written submission form.. The Technical Panel is particularly interested in comments relating to the following issues: In MR-00195-R00 does the proposed wording in section 3.5.1A provide too much flexibility to the IMO in determining the circumstances by which constrained off CMSC payments may not be allowed; In MR-00195-R00 section 3.5.6.1 is compensation in addition to the MCP equivalent appropriate to cover additional costs incurred by the Market Participant; and With respect to MR-00195-R00-06 as a whole does fairness require applying these proposed rules in equivalent situations which lead to negative CMSC such that negative CMSC payments would either be avoided or such that market participants would be credited for these negative CMSC payments.
Written Submissions Comments from Brascan Comments from Bruce Power |
Technical Panel Recommendation on Amendment Proposal R00-R06 |
IMO Board Decision R00-R06 |
MR-00192 - Emergency Demand Response Load
Effective Date: Jun 1, 2002 |
Chapter 5, Sections 4.3.2/4.8 (new) Chapter 9, Section 2 |
Board Decision At its meeting on Friday May 3, 2002, the IMO Board approved a set of market rule amendments, MR-00192 R00-R03: Emergency Demand Response Load Program. These rule amendments provide the IMO with the authority to contract for and compensate Ontario load that curtails energy consumption at the IMO's request in times of pending or actual emergency conditions on the IMO-controlled grid. The IMO Board approved these market rules under its rule making authority that was transferred to it by the Minister of Environment and Energy on May 1, 2002.
The IMO Board approved these rule amendments without invoking the full stakeholder consultation for market rule amendments that is contemplated in Section 4 of Chapter 3 of the Market Rules. The IMO Board judged that the exercise of this discretion was appropriate in this instance for the following reasons:- To enable this Program to be available, if required, within a short period following market opening.
- The IMO will be undertaking a stakeholder consultation in the development of the specifics of Program; and
- This was the only rule amendment that was still in the approval process when rule-making authority was transferred to the IMO Board, and was reviewed and recommended to the IMO Board by the Technical Panel.
Information on this stakeholder consultation can be found at: www.theimo.com/imoweb/pubs/edrp_announcement_2002may10.pdf |
MR-00161 - Treatment of Co-Generation Facilities in the Market Rules
Effective Date: Sep 10, 2003 |
Chapter 7 |
Technical Panel Determination on Amendment Submission Q00 The IMO Technical Panel invites comment on this submission by June 28, 2002. |
Written Submissions:
AES Cardinal Power DuPont Canada Inc. Lake Superior Power LP TransCanada Energy Ltd UBS Warburg Energy (Canada) Ltd. Tractabel Canada Inc., West Windsor Power Whitby Cogeneration LP |
Amendment Proposal - Request for Stakeholder Review and Comment R00-R05 The Technical Panel invites stakeholders to review and provide written comments on this draft market rule amendment proposal using the written submission form by May 12, 2003. It is particularly interested in comments regarding the issue of what would be a suitable level of efficiency (i.e. heat rate) to qualify as a cogeneration facility. This particular aspect presently is not captured within the draft proposed amendment. |
Technical Panel Recommendation on Amendment Proposal R00-R05 |
IMO Board Decision R00-R05 |
MR-00121 - Market Treatment of Facilities with Multiple Connection Points
Effective Date: Aug 19, 2006 |
Chapter 7, Section 2.3 |
Technical Panel Determination on Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this draft market rule amendment proposal and to
provide comments on the proposal to the Panel by April 16, 2004 using the written submission
form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO-Board Decision R00 |
Amendment Proposal R01-R03 (Replacement Energy Offers) The Technical Panel requests that stakeholders review this draft amendment proposal and provide comments to the Technical Panel by June 22, 2006 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R01-R03 |
IESO Board Decision R01-R03 |
MR-00053 - "Dispatch instruction" and "Dispatch message" - Clarification
Effective Date: Sep 18, 2002 |
Chapter 5, Section 12.3 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00042 - Clarification of Dispatch Data Requirements for Intermittent and Self-Scheduling Generators
Effective Date: Mar 8, 2006 |
Chapter 7, sections 3.7 and 3.8; Appendix 7.1 |
Amendment Submission Q00 |
Amendment Proposal R00 - Request for Stakeholder Review and Comment The Technical Panel requests that stakeholders review this amendment proposal and provide comments to the Technical Panel by September 16, 2005 using the written submission form. |
Technical Panel Recommendation on Amendment Proposal R00 |
IESO Board Decision R00 |
MR-00034 - Facility Registration Terminology
Effective Date: Sep 9, 2002 |
Chapter 7, Section 2.2.12, 2.2.16, 2.2.22, 10.2.2, 2.2A.2 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |
MR-00029 - Enforcement Actions Listing Amendments
Effective Date: Mar 5, 2003 |
Chapter 3, Sections 6.6.1; 6.6.2; 6.6.5; 6.6.6; 6.6.8; 6.6.9; 6.6.12 Appendix 3.1 |
Technical Panel Determination on Amendment Submission Q00 The IMO Technical Panel invites comment on this submission by August 7 2002. |
Written Submissions:
Mirant Americas Bruce Power MR-00029-Q00 Ivaco Rolling Mills |
Amendment Proposal - Request for Stakeholder Review and Comment R00-R01 The IMO Technical Panel invites comment on this amendment proposal. Submissions will be considered by the Technical Panel on December 3, 2002 to determine whether the proposal should be recommended to the IMO Board. |
Written Submissions:
Bruce Power MR-00029-R00-R01 |
Technical Panel Recommendation on Amendment Proposal R00-R01 |
IMO Board Decision R00-R01 |
MR-00027 - Rule Note - Definition of Transmitter
Effective Date: Sep 9, 2002 |
Chapter 11, Section 1 |
Technical Panel Determination on Amendment Submission Q00 |
Technical Panel Recommendation on Amendment Proposal R00 |
IMO Board Decision R00 |